Background Image

Welcome to Softsaro.

Welcome to Softsaro

Hydropower Pvt. Ltd., established on February 21, 2008, is a privately owned hydropower company based in Lalitpur, Nepal. The company is notably recognized for holding the license to develop the Marsyangdi Besi Hydropower Project, a 50 MW run-of-river plant located near Besisahar Municipality. The project is designed to generate an estimated 321.15 GWh of electricity annually, utilizing two 25 MW Francis turbines, with infrastructure including a 6.65 m tunnel, a 315 m penstock, and a semi-underground powerhouse. Electricity from the project will be transmitted to a nearby substation in Udipur, around 5 km from the powerhouse. Recently, API Power Company Limited approved the acquisition of Divya Jyoti Hydropower, signaling a move to advance the Marsyangdi Besi project. This development comes at a time when Nepal’s Ministry of Energy is actively reviewing non-operational hydropower licenses and pushing for progress in the sector, aligning with the country’s broader goal of producing up to 28 GW of electricity within the next decade for domestic use and export, particularly to India and Bangladesh.

Company Profile

  • Name: Hydropower 

  • Incorporated: February 21, 2008 (996CO)

  • Company Type: Privately owned, single-proprietor format, based in Lalitpur, Bagmati Province (996CO, Nepal Database)

  • Registered Address: Lalitpur Metropolitan City–03, Lalitpur (Nepal Database)

 

 

What’s Known

While the company is listed publicly as established in 2008 and located in Lalitpur, there’s no readily available information indicating:

  • Exact projects they’ve developed.

  • Installed capacity or operational hydropower plants.

  • Any recent developments, licenses, or active projects linked in mainstream media.

This suggests that Divya Jyoti Hydropower may be at an early stage, potentially holding licenses or in planning phases, but without well-documented executed projects.

 

 

Broader Context: Hydropower Expansion in Nepal

  • In a notable development, API Power Company Limited recently decided to acquire Divya Jyoti Hydropower Pvt. Ltd., the entity that holds the license for the Marsyangdi Besi Hydropower Project (a 50 MW run-of-river project near Besisahar Municipality). The acquisition was approved in API’s board meeting on Shrawan 27, 2082 BS (mid-2025) (996CO, Nepal Database).

  • Marsyangdi Besi Project Details:

    • Capacity: 50 MW, employing two 25 MW Francis turbines.

    • Annual Generation: Estimated 321.15 GWh (65.5 GWh in dry season, 258.65 GWh during rainy season).

    • Infrastructure includes a 6.65 m tunnel, a 315 m penstock, and a semi-underground powerhouse. The generated power will connect to a substation in Udipur, just 5 km from the powerhouse .

 

Industry Outlook & Regulatory Environment

  • The Ministry of Energy, under Prime Minister Pushpa Kamal Dahal's directive, is scrutinizing non-operational hydropower projects and may revoke licenses if progress isn't shown (myRepublica).

  • Nepal envisages a massive expansion in hydropower—with goals to generate up to 28 GW over the next decade and export a significant portion, particularly to India and Bangladesh (Reddit, Kathmandu Post).

 

Meet Our Team

Our talented team members who make everything possible

Ram Krishna

Ram Krishna

CEO

Shyam Bahadur

Shyam Bahadur

HR

Ram Bahadur

Ram Bahadur

Staff